Summary: The controversial South Brisbane exchange project has finished ahead of schedule.

SHARE:
TOPICS: Telcos, Australia
3

After 18 months of toiling, Telstra has finished converting the South Brisbane exchange's copper infrastructure to fibre ahead of schedule.

The project was a result of the construction of the new Queensland Children's Hospital on a site occupied by the old South Brisbane exchange. As a result of having to move the exchange, Telstra decided to force all premises in the area to upgrade to fibre, something that stirred up a storm of controversy within the telco industry.

The fibre network now covers 18,000 services and is made up of 284km of cable providing fibre access to 13,000 premises in the region.

During the course of the construction, Telstra laid 26.4km of new conduit and replaced or upgraded 1,661 pits. It is the largest Optical Distribution Network project Telstra has undertaken. Roughly 120 technicians were given training about fibre technology solely to work on this project.

"For anyone located in the South Brisbane exchange area, it will be business as usual from now on, as connections, disconnections, and faults on the new network will be managed directly with their telecommunications service provider," Telstra said in a blog post.

The telco will spend the next five months decommissioning the copper network and recovering copper cables, as well as recycling scrap material.

Topics: Telcos, Australia

Spandas Lui

About Spandas Lui

Spandas forayed into tech journalism in 2009 as a fresh university graduate spurring her passion for all things tech. Based in Australia, Spandas covers enterprise and business IT.

Kick off your day with ZDNet's daily email newsletter. It's the freshest tech news and opinion, served hot. Get it.

Talkback

3 comments
Log in or register to join the discussion
  • Actually the reason was....

    They had to move the exchange as the Childrens Hospital wanted the location to expand into. It wasn't just about providing increased bandwidth, it was that every cable in the area had to be re-run and not even Telstra think that laying new copper was the right way to do it.
    gr1f
    • Ta

      Corrected above, cheers.
      Chris Duckett
  • WoW NBN Employment here we come

    If the figures in the story above are correct that's 1 man for every 2.4Km of fibre. How many will be needed to roll out the NBN in Australia.
    kingvig