Summary: Telstra is in the process of revamping a 10-year-old building shell in London to support a modern high-efficiency datacentre, with the help of consulting company On365.

SHARE:

 |  Image 3 of 4

  • Thumbnail 1
  • Thumbnail 2
  • Thumbnail 3
  • Thumbnail 4
  • (Credit: Jack Clark/ZDNet UK)

    The upgrade to the 114,250-square-foot site is an attempt by Telstra to claw back power by getting rid of inefficiencies in cooling.

    The goal is to grab back around 50 to 60KW from cold aisle containment on each of the facility's nine operational floors. With this, as well as upgrades to the uninterruptible power supply (UPS) system, Telstra hopes eventually to get around a megawatt of power back.

    One of the few bits of hardware that can give Telstra trouble with controlling the temperature differential between the hot aisle and cold aisle is a type of switch from Cisco that is popular with customers. The Cisco 7600 series of routers have a tendency to blow air out of the front, which proves a headache for heat management, Kevin Sell, head of technical facilities at Telstra International, said.

  • (Credit: Jack Clark/ZDNet UK)

    Telstra uses an energy management suite of software from APC by Schneider Electric for monitoring and managing the power and cooling of the servers. The StruxureWare Central software (pictured) is used to monitor the watt drawdown and the operating temperature of servers, along with other operating factors.

    Telstra customers can key into the software via a web-based portal to look at the status — temperature, power consumption, and such — of their racks.

    By implementing Schneider APC's monitoring system, Telstra believes it's able to boost the efficiency with which it consumes power while being able to offer customers service-level agreements on power consumption and uptime backed by a mutually accessible source of data.

    Monitoring "encourages good behaviour on both sides", Sell said. "If [customers] say 'last night my temp went over 24 degrees Celsius', we can't deny it."

  • (Credit: Telstra)

    For the future, Telstra plans a major project to get rid of heat by using the water in its London Docklands surroundings to chill the water it uses.

    "We've applied to British Waterways to dispose of 3MW of heat into the dock, which British Waterways has approved," Sell said. "We're just waiting on the Environment Agency." He explained the system will be a "massive heat exchanger" that makes use of the relatively cool waters of the wharf for chilling.

    "That should give us almost year-round practically free cooling," he said.

    Via ZDNet UK

Topics: Cloud, Hardware, Servers, Storage, Telcos, Telstra

Jack Clark

About Jack Clark

Currently a reporter for ZDNet UK, I previously worked as a technology researcher and reporter for a London-based news agency.

Kick off your day with ZDNet's daily email newsletter. It's the freshest tech news and opinion, served hot. Get it.

Related Stories

Talkback

0 comments
Log in or register to start the discussion