Contents ![]() ![]() ![]() ![]() ![]() | ||||
With outsourced deals generally becoming more fragmented, the effect of getting things wrong is increasing. James Longwood, research vice president, sourcing, at Gartner Asia Pacific says any cross-ESP issues are becoming more difficult to manage as companies move towards more selective sourcing contracts. "For example there might be boundary problems -- is it the database, the central application, the network or the desktop the real problem and what happens when each ESP points the finger at the other ESPs in the service delivery change?" he asks.
On the flip side, from a contractual perspective, flexibility when things go wrong is a possible upside of selective sourcing, says James Hunter, head of outsourcing at Cap Gemini Australia.
"The very fixed, very robust contracts offered very little in the way of flexibility and there were all these issues about what the contract said and what was actually happening. The dilemma was between staying with a contract or not complying with it and trying to deliver something that makes sense," he adds.
Blacklaw says the positive slant of outsourcing is that an ESP "might have the testosterone or the commercial backing to just say no to a suggestion, and give reasons." But that's the positive slant, he says. "The negative slant is that by having an outsourced contract in place there may be an expectation that the corporation has transferred accountability which clearly lies within their responsibility. The provider might say 'you outsource to me, I do all this stuff, and then let's test it,' but if the client has put together a poor test case they might not find any errors in the solution," says Blacklaw. And whose fault is that?
Contents ![]() ![]() ![]() ![]() ![]() ![]() | ||||
Longwood says when it comes to BPO, often the service providers understand delivering business services but not the IT sides of things. "They often have poor SLAs and don't have good interface specifications between their systems and clients. For example, they might do accounts payable and receivable well for you but are slow or inaccurate at transferring the general ledger transactions to your internal ERP system negatively impacting the accuracy and timeliness of an enterprises profit and loss statement," he says.
Geography also plays a role, particularly on offshore outsourcing. "We see lovely figures of 40 or 50 percent cost reduction when it comes to offshoring, but unless you fully understand the risk of offshore locations, and that each one has different risk dynamics, the cost differential won't be realised," says Capgemini's Hunter.
Offshoring throws up significant extra project management overheads, with risks coming from all directions -- political unrest, socio-economic factors, terrorism, relationships with other countries, border tensions, Government policies with regards to taxes, duties and other regulations. In addition you might have to deal with cultural, language and communication issues, security and privacy, knowledge transfer, business continuity and change management, as well as the financial viability of the supplier and price inflations.
Contents ![]() ![]() ![]() ![]() ![]() ![]() | ||||
KAZ's Richardson strongly recommends that if you haven't done any formal business risk audits of your outsourced project, you should invest the time and money to do so, to give you a characterisation of risk in terms of severity. "Do it before the contract if possible to provide ammunition," he says. If you have done an audit and have a trusted partner, as business changes happen you can move much faster. This is especially true as companies move towards selective sourcing contracts.
Blacklaw believes there are two major risk mitigation strategies. "Firstly, for large projects spanning years, you need to have an independent quality assurance assessment (QA) done. If I'm building a $25 million system, I would need, every six to 12 months, to have independent QA done of my program, and I would want to know what the program director was doing every six to eight weeks to check whether he or she is pulling anything over my eyes," says Blacklaw. "It's important for the project manager to get into the discipline of reporting to stakeholders, and the CFO, who can sit there and ask the dumb ass question of why certain things are being done a certain way," he adds.
Finally, there is often a mistaken view that a fixed price contract manages risk, says Blacklaw. "You get a fixed price but not a fixed quality. It's impossible to fix the price from inception, because things change every single day, and if variations and changes are required, it forces the organisation to make guesses and the project may end up costing more," he says. "Seven years ago companies like IBM and EDS were moving into fixed cost deals, but there are have been some infamous examples of major losses incurred over fixed price contracts because the scope is never clearly defined, there is scope creep, and the customer thinks he or she has paid for X plus two and the vendor thinks its X minus one," he adds.
Contents ![]() ![]() ![]() ![]() ![]() ![]() | ||||
Dimension Data's general manager of service delivery Karen James says if you spend a lot of time mitigating risk, it doesn't need to be written into a contract.
"We involve ourselves in a lot of risk mitigation, rather than putting it into the costing, which we believe is not an effective approach," she says. James says some penalties are just there to crawl back money but are not in the supplier's control. She uses the example of outages per month at a site or a device. "There are a lot of possible reasons for this, but do you write this all up or do you ask if this is a realistic measure of performance," she says. "If a vendor has a problem, is that the service provider's fault?"
James says that in some cases, even if an SLA is in place and is met, the client might still penalise the supplier. "If you go into those sort of agreements, the risks aren't in your control, so you could fix the problem but there might be an overriding clause that says the client can penalise the supplier. It sounds crazy, but there are service contracts out there that do that," she adds.
Marks says people have become better at accepting or mitigating risk and that has made it more comfortable to manage the process before signing the contract and during delivery. There has also been a greater focus on delivering best practice and on using methodologies such as ITIL.
"There is a greater understanding that the supplier's business might change during a contract and adjustments need to be made," he says. "We capture details in one engagement and constantly learn from it. With the ongoing threat of new types of security attacks, we've got to be clear that when we identify one risk, the lessons can be applied across all our other engagements," he adds.
So important is the increase of risk, it's something that should be considered at the top level of the business, says KAZ's Richardson. "Information and communication technology is becoming ever more pervasive and more mission critical, and as this happens, dependence on effective risk management increases," he says. "This is a boardroom issue, fair and square."
Contents ![]() ![]() ![]() ![]() ![]() ![]() | ||||
End users felt that over a period of time the service levels degrade. The reason for this again could again be a lack of clarity in agreements at the outset of the contract and with the demanding end users expecting more for less over the period of the contract, the vendors are sometimes forced to protect their bottom line margins and this could lead to a reduction in service levels.
In contrast, a look at the 2003 survey showed that potential loss or reduction in service levels was the second major risk of outsourcing followed by unrealised cost savings. The 2004 survey places unrealised cost savings at the second place and potential loss of service levels has been pushed further down. There is a positive indication in this, which shows that vendors have definitely focused on improving their service deliverables to their customers and defining strategies for reducing risk before the outsourcing contracts are signed off.
Some of the other risks associated with outsourcing were:
Contents ![]() ![]() ![]() ![]() ![]() ![]() | ||||
Typical Risk / CSF | Approach to Mitigation |
Project doesn't meet business goals. | Develop a sound business case, including risk and cost benefit assessment. Include costs for go to market, transition and on-going sourcing management. |
Wrong services are outsourced or wrong ESP is selected. | Develop a sourcing strategy analysing internal versus market capability. Properly assess sourcing models available. |
Services are not clearly defined resulting in poor service deliveries. | Develop a comprehensive statement of service / project requirements, into a formal Statement of Work with appropriate service levels. |
Internal staff may be un-co-operative in efforts to outsource. | Establish an organisational change management strategy early in the piece with a very good and open communication approach. |
Deal becomes quite inflexible over time. | Ensure appropriate mechanisms to change base line of services and to introduce new innovative technologies or services. |
Early cost savings followed by unexpected cost blow outs. | Ensure appropriate mechanisms for changes to base line services, that pricing is visible and fair for changes in scope of services. |
ESPs buy the business and then can't deliver and ask for an increase in fees. | Enterprises must learn to evaluate costs last and not first when evaluating and selecting ESPs. Evaluate their service delivery capability and track record and service delivery / SLA management capability first and eliminate ESPs who can't meet your requirements before comparing prices. Understand that ESPs must make a profit in order to continue to deliver a high quality of service and invest in process improvement programs. |
This article was first published in Technology & Business magazine.
Click here for subscription information.